Rapid progress has already been made since the demolition and renovation phase of the Mill Lane development began in July 2021.
Bird's eye view of College and Mill Lane
Bird's Eye Image of Mill Lane Building Site
Aerial view of Mill Lane building site and down Trumpington Street
Scaffolding around buildings 75 and 76 Trumpington Street and the foyer of the former Emmanuel United Reformed Church
Scaffolding around 75 and 76 Trumpington Street
Entrance to the building site on Mill Lane
Gaps left by the demolition of the foyer to the Emmanuel United Reformed Church and 75 Trumpington Street
Demolition of 75 Trumpington Street leaves brickwork of No. 76 exposed
Scaffolding around 4 Mill Lane
Mill Lane building site, showing the demolition of 75 Trumpington Street and Emmanuel URC foyer from the rear - December 2021
Rose window in Emmanuel United Reformed Church before cleaning and renovation
Scaffolding in the interior of the former Emmanuel United Reformed Church
Board Room of Stuart House undergoing renovation
Room in 4 Mill Lane undergoing renovation and repair
All photos were taken between July to December 2021. Photos 1-3 copyright Hannah Constantine and Haworth Tompkins.